Record the client's payment notice and payment

The Payment notices section sits below the applications on the Applications made page. It shows, for each submitted application, the dates the client has to meet and lets you record what the client sends back.

Steps

  1. Open the project, choose Applications, then the Payment dates section. A submitted application, opened from the Submitted tab, shows its own Payment notices too.
  2. Find the application under "Payment dates". Each one shows its status and four dates, each marked upcoming, received or passed.
  3. When the client sends a notice, select Record client's notice.
  4. Under "Which notice is it?" choose Payment notice or Pay less notice.
  5. Enter the Notified sum (£) and the Date on the client's notice. Add the Client's reference and a Note if you want.
  6. Select Record notice. After that, "Notified sum", "Net applied for" and "Difference" are shown for the application.
  7. To keep the client's own document, select Attach client's notice and choose a PDF.
  8. When the money arrives, enter the date under "Payment received on" and select Record payment received.
  9. If your firm is connected to Xero and the invoice is already there, payment is read from Xero instead. Select Check Xero now to read it straight away. The line then shows "Awaiting payment in Xero" or the amount paid.

If the page shows "Not sent to Xero", select Retry. After a send, Resend to Xero sends it again.

What happens in Xero

The application's invoice is in Xero, and payment is read back from there. If your firm sends the invoice when payment is received, selecting Record payment received raises the invoice in Xero and records the payment against it. That needs a bank account chosen in Settings → Xero; if it is missing, the page says so and links to it. The VAT invoice setting on this page applies only to firms not connected to Xero.

Construction Act notice dates

The page works out four dates from the valuation date and your Contract terms:

  • Due date: the valuation date plus "Due after valuation date (calendar days)".
  • Final date for payment: the due date plus "Final date after due date (calendar days)".
  • Payment notice deadline: the due date plus "Payment notice after due date (calendar days)".
  • Pay less notice deadline: the final date for payment minus "Pay-less notice before final date (calendar days)".

The dates are frozen with the terms at the time of the application. A date shows "received" when the matching notice or the payment is recorded. If the final date passes without payment, the page offers the suspension notice, and a late payment interest panel appears.

More in The monthly cycle