Make an application to the client

The Applications made page lists your applications under Draft and Submitted tabs and is where you apply to the client for payment against the contract sum. Open a project, then choose Applications. Once an application is submitted it is fixed, so put any correction in your next application.

Before you start

The page needs a contract sum. If none is entered, open the Contract sum tab and enter it first (the page shows "Enter the contract sum to make your first application"). The payment dates in the next article come from the terms on the Contract terms tab, so set those before you submit your first application.

Steps

  1. Open the project and choose Applications.
  2. Select New application. In the "Make an application" panel, set the Valuation date and select Create draft.
  3. The new application is listed under the Draft tab (the other tab is Submitted). Select its heading to open it.
  4. For each contract line, choose the Measure (Percent or Quantity) and enter the cumulative progress to date. Enter the total to date, not just this month's work.
  5. If the project has variations, enter Cumulative progress (%) against each one. A variation marked "Assessed, not agreed" is valued at your own assessment.
  6. Enter Materials on site (£) and, if you want, VAT information. Add materials items if the page asks for evidence.
  7. Check "Live application calculation". It shows works to date, materials, gross to date, previous applications and "This application". Retention is deducted below it.
  8. Select Save draft. Use "Preview application PDF" to see the document before it is issued.
  9. Select Submit application, then Confirm submission. If a check on the page asks for a reason (for example, a line lower than last time), type it in before you submit.
  10. After submission the application moves to the Submitted tab. Open it and select Email to client to send the application to the client's contacts. The button changes to "Email to client again" and each send is listed with its date and recipients.
  11. Optionally select Generate private PDF, then fill in the document fields and select Register valuation document to file it in the project's documents.

What happens in Xero

If your firm is connected to Xero, the application is sent to Xero as the invoice for this customer order. When it is sent depends on the setting on the customer order, shown on the Payment notices section as "Send to Xero". A sent invoice shows its status on the application. If it fails, the failure is shown with a Retry button.

Construction Act notice dates

Submitting an application does not by itself work out the dates. The payment dates are worked out from the valuation date and your Contract terms, and are shown under "Payment dates" in the next article (Record the client's payment notice and payment).