Read the cost report

The Project cost report compares your budget, the orders you have placed and what has actually been spent, by cost head. Open a project and choose Cost report. The tabs at the top are Cost report, CVR and Change register; this article is about the first.

Reading the table

Each row is a cost head. The columns are:

  • (1) Budget.
  • (2) Orders placed: issued subcontracts and purchase orders, including variations and hire.
  • (3) Orders still to place: the budget less orders placed until you enter a figure.
  • (4) Provisions.
  • (5) Estimated final cost: orders placed plus still to place plus provisions.
  • (6) Total variance: budget less estimated final cost.
  • (11) Costs to date, with value done: Xero costs plus accruals, with the value done shown under it.
  • (14) Cost to complete.

A red "Committed over budget" tag means orders placed exceed the budget. An amber tag means certified or committed is more than 10% above value done. The Project total row adds everything up. Own labour from timesheets appears below the table.

Steps

  1. To change a figure, type in the "Still to place for" or "Provisions for" box on the row. Clear the "Still to place" box to return to the calculated figure.
  2. To enter a figure for a head with no row, use Cost head, Still to place (£), Provisions (£) and Save estimate entry.
  3. To record a cost received but not yet invoiced, use Cost head code, Amount (£) and Note, then Add accrual.
  4. Select Download CSV or Download PDF to take a copy.
  5. Use "Orders placed, by cost head" to see which orders make up each figure.

You need budget-write access to change figures. If a project has no budget, the page offers to set one.

What happens in Xero

The report reads approved and paid bills, supplier credit notes and spend money tagged to this project in Xero. Nothing you enter here is sent to Xero. See "Costs coming in from Xero, and costs to code" for refreshing and coding.

Construction Act notice dates

The cost report does not work out any Construction Act notice dates.