Assess a subcontractor's application and issue the payment notice

The Subcontract orders page lists the orders you have issued on a job. Under each order, "Applications" is where a subcontractor's applications are recorded, assessed and answered with a notice.

Steps

  1. Open the project, choose Subcontract orders, and open the order from the list (issued orders are under the Issued tab).
  2. Under Applications, enter Period start and Period end and an "Initial % on every line", then select Record application. If the firm sets up payment documents, choose the Payment document first: "Subcontractor sends its own invoice", "Self-billing (needs a written agreement)" or "Authenticated receipt (subcontractor signs and returns)".
  3. Select the application's heading to open its table.
  4. In the "Assess cumulative" column, enter the value you assess for each line to date. Use the Comment box for any line you reduce.
  5. Use "Add on-account amount" to include an amount against a variation, and "Add deduction" for any deduction (description, quantity, unit, rate, reason, and who to recharge).
  6. Select Record assessment. The application becomes assessed and "Download payment certificate (PDF)" appears.
  7. Under "Issue a notice", choose the Notice (Payment notice or Pay less notice), enter the Reference and the Date issued, and fill in "Basis for this notice" (for a pay less notice, "Basis for what we will pay"). Add a reason for any line if you want.
  8. Select Issue payment notice (or Issue pay less notice). The notice is recorded, filed and emailed to the subcontractor. If sending fails, the notice is shown as recorded, not sent, with a Retry button.
  9. To bill it, select Send bill to Xero. For a subcontractor who sends its own invoice, enter the Subcontractor's invoice number and the Subcontractor's invoice date first.
  10. Use Check Xero now to read payment back from Xero.

What happens in Xero

Send bill to Xero creates the subcontractor's bill in Xero for the assessed amount, with the project and cost heads on its lines. If the subcontractor's CIS details are missing in Xero, nothing is sent and the page links to the contact. A failed send shows an error and a Retry button. Payment is read back from Xero, and the application shows when it is paid.

Construction Act notice dates

For each application the page shows four dates and whether each has been met: Due date, Payment notice deadline, Pay less notice deadline and Final date for payment. They use the subcontract's own payment terms when it has them. Otherwise they use the Scheme defaults: due 7 days after the later of the period end and the application date, payment notice 5 days after the due date, final date 17 days after the due date, and pay less notice 7 days before the final date. The notice deadlines count from when the notice is sent to the subcontractor, so a notice sent after its deadline is marked "Sent late". If neither notice is given in time, the page says "No notice received in time: your application stands as the sum due."