Issue the month-end and its CVR
The CVR tab on the project cost report is the month-end close. CVR means cost value reconciliation: it sets the value you have earned against the cost to date for a month. Issuing the month freezes the estimated final cost, the CVR and the work in progress figures for that month.
Steps
- Open the project, choose Cost report, then the CVR tab.
- Under Month, choose the month and select Start month. Only one draft month can be open at a time, and a month must be later than the last issued one.
- If the tab lists "Costs to code that could belong to this project", select Code to this project or Not this project on each line. You can issue with some still open; the count is recorded.
- Under "EFC period: head comments", type a comment for each cost head that moved by more than the threshold and select Save comment for that head. EFC means estimated final cost. A month cannot be issued until each such head has a comment.
- Fill in the adjustments: Over/under-valuation (£, negative for over-valuation) with a Reason, Provisions for value risk (£), and Provisions for cost risk, entered (£).
- Tick any risks under "Provisions for cost risk from the project's risk register" and enter a provision for each.
- Under "Subcontract liability for work done but not yet applied for", tick an order and choose "Enter amount (£)" or "Calculate from % complete".
- Select Save adjustments to keep your work. Figures update until the month is issued.
- Check the table against the movement on the last issued close.
- Select "Review and issue month (freezes the EFC period, CVR and WIP)". By default the person who prepared the month can issue it. If your firm turns on "Require someone other than the preparer to issue each month end" (Settings, Cost heads, Estimated final cost), someone else must issue it. Every issued month shows both who prepared it and who issued it.
- Select Discard draft to throw a draft month away instead.
An issued month shows who issued it and when, and its figures cannot change. Choose an earlier month from the buttons to read it.
What happens in Xero
Nothing is sent to Xero when you issue. The costs used come from the last read from Xero, and any uncoded cost lines are listed on this tab so you can code them. Coding a line here writes the project onto that line in Xero.
Construction Act notice dates
The month-end does not work out any Construction Act notice dates.