Variations to an order
The Variations page (open a project, then Variations) lists the variations on the job, newest first, with the New variation form below the list. It has no status tabs; each variation shows its status beside its title. A variation can be linked to a subcontract order, so the agreed value adds to that order. Changes to the order's own terms are made with Amend on the order instead.
Create a variation
- Open the project and choose Variations.
- In the New variation form below the list, choose a Subcontract order (or None). To start from an RFI or a delay, select Create variation from this RFI (or delay) under "Create a variation from an RFI or delay".
- Enter the Description, Cause and Time impact (working days).
- Add lines with Add line: description, quantity, unit and rate. The Total updates.
- Select Create variation. Use Edit draft and Save draft to change it later.
- Select Submit and file. The variation is filed as a document, using the Register identity for submission.
Assess and decide
- Enter the Assessed value (£) and select Save assessed value. This records your assessment but does not agree it.
- To agree it, enter the Agreed value (£), choose a Cost head and select the agree button. Select Reject to decline it.
- Withdraw agreed variation undoes an agreement. Withdraw cancels a draft or submitted variation.
What happens in Xero
Nothing is sent to Xero when you create or agree a variation. The agreed value changes the order's value, which is what later bills and applications are measured against.
What the subcontractor sees by link
The variation is not shown on the subcontractor's order link as a separate page. A variation linked to a subcontract order is included in the order value, and in the lines they apply against. Send the registered document to them from the document register (Open registered document).