Plant hire and off-hire

Plant is hired on a purchase order line marked as hire. The Hire lines table on the order shows each item's On hire date, Expected off-hire, Off-hired date and days. When the plant is no longer needed you ask the supplier to collect it.

Hire plant

  1. On the project's Purchase orders page, select New purchase order.
  2. On the line, tick "is hire" and choose the rate basis. Enter the On hire date and, if known, the Expected off-hire date.
  3. Select Save purchase order and issue the order as usual (see Raise a purchase order).

Request off-hire

  1. In the Hire lines table, find the line and select the request button in the Off-hire column.
  2. Enter the Off-hire date and check the Collection address (it starts as the site address).
  3. Under Send to, choose a supplier contact. If the order goes to a branch, the branch email is shown instead.
  4. Select Send off-hire request.

The cell then shows the request and the date the supplier has to confirm by. If the email failed it says "Send failed — resend". The Deliveries page lists requests under Off-hires awaiting confirmation.

If the supplier does not confirm by the date, the hire ends on the date you requested and is marked as unconfirmed by the supplier.

What happens in Xero

Off-hire does not change anything in Xero by itself. The hire charge on the supplier's bill is checked against the hire dates when the bill arrives.

The email carries an off-hire link that needs no account. It shows the item, site, collection address and requested date. The supplier enters Your off-hire number, the Off-hire date and Your name, then selects Confirm off-hire. Their confirmation appears on your order with the off-hire number. Suppliers can also confirm from their order link.

More in Purchases