The look-ahead on site

The Look-ahead tab of the Site app (/site/lookahead) shows the programme's activities for the coming weeks, so the site team can see what is due to start and what is late. It is built for a phone.

Read the look-ahead

  1. Open Site, choose the project, and select Look-ahead.
  2. Choose 2 weeks or 3 weeks in the Look-ahead window.
  3. Activities are grouped under Week commencing dates. Anything behind appears under Late to start.
  4. Each activity shows Ready or Not ready when planning conditions are set.
  5. Select Print for a paper copy.

Update an activity

  1. Select an activity to open its details: Start, Finish, Owner / trade, % complete, Critical, Total float, Predecessors, Successors and Notes.
  2. Select Started or Finished, or type the % complete.
  3. Close the sheet with ×.

You can only change activities if you have permission, and not on an archived project or a programme imported as read-only. The same view is available on a computer.

What happens in Xero

Nothing is sent to Xero.