The programme

The programme is the project's plan: sections of work, activities with start dates and durations, and the links between them. Dates are counted against the project's working calendar.

Build the programme

  1. Open the project, then Programme.
  2. To bring in a plan from planning software, select Import and follow the prompts. An imported programme can be read-only ("Master") or managed here.
  3. Select Add section and type a Section name, then Add section.
  4. Select + Add activity. Enter Activity name, Section, Start date and Duration · working days. Optionally set Owner or Trade, Completion · percent and Notes. Select Add activity.
  5. To link activities, open one, find Add link, choose Related activity, This activity is a (Successor of or Predecessor of), Link type (Finish to start, Start to start, Finish to finish, Start to finish) and Lag · working days, then select Add link.
  6. To stop an activity starting too early, enter Start no earlier than and select Set constraint (Clear constraint removes it).
  7. Select Working calendar to set the standard working week and Add date exception for non-working dates.

Keep it up to date

  1. Switch the timeline between Week and Month, and select Today to jump to the current date.
  2. Open an activity and update Completion · percent, then Save activity.
  3. Select Save baseline to freeze the current plan; the activity then shows Baseline start and finish and the variance.
  4. Select Print / export for a printable copy.
  5. If the project has no order lines yet, Create lines from programme builds them from your activities.

What happens in Xero

Nothing is sent to Xero from the programme.

More in Setting up a job